Edge Router Upgrade - B Side - London Datacenter

Scheduled Maintenance Report for Linode

Completed

The scheduled maintenance has been completed.
Posted Jun 03, 2018 - 05:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 02, 2018 - 23:00 UTC

Scheduled

On Saturday, June 2, at 23:00 UTC (Sunday 00:00 British Summer Time), our engineers will be performing an edge router upgrade in our London Datacenter. We will be working exclusively on the “B” side of the network, and do not expect any downtime during this maintenance as we have full router redundancy. However, brief periods of packet loss or increased latency may be observed at times. We expect this maintenance to take 6 hours
Posted May 22, 2018 - 16:33 UTC
This scheduled maintenance affected: Regions (EU-West (London)).