Scheduled Network Maintenance - Fremont

Scheduled Maintenance Report for Linode

Completed

The scheduled maintenance has been completed.
Posted Jun 27, 2019 - 13:00 UTC

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 27, 2019 - 11:00 UTC

Scheduled

On Thursday the 27th of June at approximately 11:00 AM UTC we will be performing a standard upgrade to one of our switch pairs in the Fremont data center.

Due to the redundant nature of these systems, we do not expect an impact to customer traffic or downtime during this process. As with any network maintenance, the possibility exists of some latency and packet loss during the window. The duration of this maintenance will be 90 minutes.
Posted Jun 24, 2019 - 13:45 UTC
This scheduled maintenance affected: Regions (US-West (Fremont)).